Micro planning in XP

Continuing the series on Extreme Programming (XP), PRADYUMN SHARMA discusses the planning process of this methodology and shows how it helps achieve results

In the previous article, we had discussed some aspects of ‘The planning game’, an important practice of Extreme Program-ming (XP). To summarise the points from the previous article before we discuss this practice further:

  • At the start of each release, a release plan is made, based on the selection of user stories by the customer. The key factor in making this selection by the customer is the value that each user story would add to them.
  • Within an iteration, at the start of each iteration (typically of one/two/ three weeks duration), user stories from the current release plan are broken down to smaller tasks of a few days duration, and developers commit to the individual tasks. Also included in an iteration plan are any incomplete user stories from the previous iteration.

Executing the iteration plan

As an iteration gets underway, programmers start implementing the programming tasks they have committed for. They seek partners to pair with them, write test cases for their tasks, write the code for implementing the tasks, and integrate their code with the rest of the system.

The onsite customer is available to the team for providing clarifications from time to time as the team members proceed with their implementation. The customer also writes acceptance tests for user stories taken up for the current iteration. As soon as a programming task is reported to have been completed by a programmer, the acceptance tests are run to verify that it works as required.

The daily huddle

You start every day with a small, 15-minute meeting of the entire team, including the onsite customer. This meeting is not held in a round-table conference room, but is a stand-up meeting, preferably held around the coffee vending machine. The stand-up nature of the meeting ensures that it does not linger on unnecessarily.

I like to call this a daily huddle, as it is more like the famous ritual of the Indian cricket team, before the start of every innings of the opponent, or after the fall of every wicket.

In this meeting, there is a quick review of the project status and of current programming tasks on hand. Everybody updates everybody else on the progress made. Small achie-vements of the previous day’s work are celebrated, ideas are thrown around and shared, and plans for the day are made, pair partners are sought. If there are problems or roadblocks, slippages, disappointments, they are also discussed and corrective actions are chalked out.The customer is also a part of this meeting. This gives the customer a good idea of the progress (or lack of it), the issues being faced, the likely completion status, etc. The customer may also be able to provide some suggestions about changes in priorities, alternative approaches that may work, etc.

Involvement of the customer

As can be seen from the above discussion, there is a significant involvement of the customer in the planning process, along with the developers. It is, in fact, a mutual, consultative approach of planning where the customer and the developers both play equally important roles.

The customer chooses the scope based on the value added by user stories, and decides the priorities. The customer also decides about the dates of releases and the composition of these releases. But these are not arbitrary, unilateral decisions.

Developers make estimates for all user stories and smaller programming tasks. These estimates are not forced from the top by someone. Detailed scheduling within a release is also decided by the developers, with the view of tackling the greatest risks at the earliest instance. Of course, it calls for an open, mature and honest team to make reasonable estimates, and not pad them up with buffers.

Developers also make the technical decisions and evaluate their consequences. Even the fine-tuning of the entire process is done by them.

Metrics

You need to measure things to see how they stack up against plans. XP projects have their share of metrics for this purpose, although the emphasis, expectedly, is on keeping them small in number and simple to use.

For example, the velocity (ratio of estimated development time to calendar time) is estimated in the planning process. But what is the actual velocity achieved by the team? So, somebody collects the data for maintaining this metric and plots it on a chart where every team member can see it.

There is no prescribed set of metrics. Have a few metrics, based on what are the main problems that the team is facing or the areas where improvements are sought. If you find that enough tests are not being written, devise a metric for measuring the adequacy of tests, and update it regularly.

Once the problem area has been brought under control, discard the metric and move on to some other problem.

The benefits

The benefits of the XP approach of planning are many:

  • It truly empowers the developers, enabling them to make all the technical decisions and effort estimates. This makes them motivated and excited about the project.
  • Customers are involved in the entire planning process, thereby making them better aware of the progress being made as well as the problems being faced.
  • Small releases and small planning cycles give the entire team a more realistic picture of project and its planned activities. You cannot anticipate or plan what you would be doing four months later, but you can better predict and control what you would be doing ten days from now.

Pradyumn Sharma is the CEO of Pragati Software. He is a trainer and consultant in the areas of Object-Oriented Analysis, Design, Design Patterns and Extreme Progra-mming. E-mail: pradyumn. sharma@pragatisoftware.com

<Back to top>


© Copyright 2003: Indian Express Group (Mumbai, India). All rights reserved throughout the world. This entire site is compiled in
Mumbai by The Business Publications Division of the Indian Express Group of Newspapers.
Please contact our Webmaster for any queries on this site.